The Trinity Place Proposed (Rough) Timing
SEPTEMBER 2007 - LEASE IS EXECUTED WITH COUNTY/SCHOOL DISTRICTJANUARY 2008 - COUNTY/SCHOOL DISTRICT BEGIN ON NEW REPLACEMENT FACILITIES
MARCH 2008 - BOYER/HOUSING PARTNER CLOSE ON A-8 LAND AND BEGIN WORK ON CIVIL/ACRHITECTURAL DRAWINGS
JUNE 2008 - OBTAIN ALL ENTITLEMENTS FOR A-8 RESIDENTIAL
AUGUST 2008 - BEGIN CONSTRUCTION ON A-8 RESIDENTIAL
APRIL 2009 - A-8 FIRST RESIDENTIAL UNITS COMPLETE
MAY 2009 - COUNTY/SCHOOL DISTRICT MOVE TO NEW FACILITIES
JUNE 2009 - BEGIN REMEDIATION/DEMOLITION OF COUNTY/SCHOOL DISTRICT BUILDINGS
SEPTEMPER/OCTOBER 2009 - BEGIN SITE WORK ON THE TRINITY PLACE
NOVEMBER/DECEMBER 2010 - GRAND OPENING OF THE TRINITY PLACE